Dadun station

Dadun

大墩
Platform
Chinese name
Chinese大墩站
Transcriptions
Standard Mandarin
Hanyu PinyinDàdūn Zhàn
Yue: Cantonese
Yale RomanizationDaaihdēun Jaahm
JyutpingDaai6deon1 Zaam6
General information
LocationIntersection of Heyue Road (荷岳路) and South Wenhua Road (文华南路) (under planning), Lecong
Shunde District, Foshan, Guangdong
China
Coordinates22°57′23.36″N 113°7′25.79″E / 22.9564889°N 113.1238306°E / 22.9564889; 113.1238306
Operated byFoshan Metro Operation Co., Ltd.
Lines     Line 3
South section
Platforms2 (1 island platform)
Tracks2
Construction
Structure typeUnderground
AccessibleYes
Other information
Station codeF318
History
Opened28 December 2022 (2022-12-28)
Services
Preceding station Foshan Metro Following station
Dongping Line 3
South section
Yuebu
Location

Dadun station (Chinese: 大墩站; pinyin: Dàdūn Zhàn; Cantonese Yale: Daaihdēun Jaahm) is a station on Line 3 of Foshan Metro, located in Foshan's Shunde District.[1] It opened on 28 December 2022.[2][3]

Station layout

The station has an island platform under Wenhua South Road.[4]

G - Exits A-D
L1
Concourse
Lobby Ticket Machines, Customer Service, Shops, Police Station, Security Facilities
L2
Platforms
Platform 1  3  towards Zhongshan Park (Dongping)
Island platform, doors will open on the left
Platform 2  3  towards Shunde College Railway Station (Yuebu)

Entrances/exits

The station has 4 points of entry/exit. Exits A and B are located on the south side of Heyue Road, whilst Exits C and D are located on the north side. Exits A and C are accessible via elevators.[1]

  • A: Heyue Road
  • B: Heyue Road
  • C: Heyue Road
  • D: Heyue Road

History

On 31 August 2016, the pilot section of Line 3 (this station to Wanhua station) started construction to cooperate with the construction of the Guangzhou–Foshan circular intercity railway.[5] The station began enclosure construction on 16 March 2017[6] and officially started excavation on 5 December 2018.[7]

On 27 April 2017, the first tunnel shield of Line 3 (from this station to Dongping station) was successfully launched.[8] The tunneling shield broke through on 8 December the same year[9] and handed over for track laying on 31 August 2020.[10]

On the morning of 19 April 2019, the pouring construction of the first basement floor of the station was successfully completed.[11] On 21 November the same year, the station became the first station on the whole of Line 3 to top out.[12]

On the afternoon of 7 August 2020, the right line tunnel from this station to Shuikou station (now Yuebu station) broke through.[13] The tunnel section passed acceptance on 7 April 2022.[14]

The station passed the civil acceptance on 2 November 2021.[15] On 30 May 2022, the station completed the "three rights" transfer.[16] On 28 December the same year, the station opened with the opening of Line 3.[17]

Usage

The nearby surroundings of this station are fishponds and farmland, and there is little flow of people, so it was dubbed "the most down-to-earth subway station" by netizens during its initial opening. At the same time, some entrances/exits of the station were blocked by river inflows, and passengers needed to take a detour for several minutes to reach the municipal road after leaving the station.[18]

References

  1. ^ a b "大墩" [Dadun]. Foshan Metro (in Simplified Chinese). Foshan Metro.
  2. ^ 北青网 (28 December 2022). "广东佛山地铁3号线首通段正式开通运营" [The first section of Guangdong Foshan Metro Line 3 officially opened for operation] (in Simplified Chinese). Retrieved 21 July 2024.
  3. ^ "Foshan opens metro Line 3". Metro Report International. 29 December 2022. Archived from the original on 8 May 2024. Retrieved 21 July 2024.
  4. ^ 何永成 (26 November 2019). "工程快讯|三号线大墩站主体结构顺利封顶" [Project News: The main structure of Dadun Station on Line 3 has been successfully capped]. Foshan Railway Investment and Construction Group (in Simplified Chinese). Archived from the original on 18 June 2022. Retrieved 21 July 2024 – via "Foshan Metro" WeChat Official Account.
  5. ^ 曾群善 (1 September 2016). "佛山地铁三号线先行段开工" [Construction of the first section of Foshan Metro Line 3 begins]. Southern Metropolis Daily (in Simplified Chinese). Archived from the original on 26 June 2019.
  6. ^ 钟静文 (1 May 2017). "顺德人必看!顺德路网改造最全收集,附绕行攻略!" [A must-read for Shunde residents! The most comprehensive guide to Shunde's road network renovations, including detour strategies!]. Zhujiang Business Daily. Archived from the original on 18 June 2022 – via Foshan Online.
  7. ^ "三号线|大墩站二期基坑正式开挖" [Line 3 - Dadun Station Phase II foundation pit officially excavated]. Foshan Railway Investment and Construction Group (in Simplified Chinese). 10 December 2018. Archived from the original on 18 June 2022. Retrieved 21 July 2024 – via Foshan Metro Official WeChat Account.
  8. ^ 高绮桦 (28 April 2017). "首台盾构机东平站始发" [The first shield machine started from Dongping Station]. Nanfang Daily (in Simplified Chinese). Archived from the original on 18 June 2022 – via Sina.
  9. ^ 李传智 (9 December 2017). "佛山最长地铁首个盾构区间贯通 可连广州多条地铁线" [Foshan's longest subway line completes first shield tunnel section, connecting to multiple Guangzhou subway lines]. Guangzhou Daily (in Simplified Chinese). Archived from the original on 18 June 2022 – via Sina News.
  10. ^ 林嘉慧; 王澍 (10 September 2020). "佛山地铁多个重大节点实现突破" [Foshan Metro achieves breakthroughs in several key nodes]. Foshan Daily (in Simplified Chinese). Archived from the original on 26 November 2020 – via People's Daily Online.
  11. ^ "三号线|大墩站二期顺利完成首仓底板施工" [Line 3 - Dadun Station Phase II successfully completes first warehouse floor construction]. Foshan Railway Investment and Construction Group (in Simplified Chinese). 22 April 2019. Archived from the original on 18 June 2022. Retrieved 21 September 2025 – via Foshan Metro Official WeChat Account.
  12. ^ 何永成 (26 November 2019). "工程快讯|三号线大墩站主体结构顺利封顶" [Project News - Main structure of Dadun Station on Line 3 successfully topped out]. Foshan Railway Investment and Construction Group (in Simplified Chinese). Archived from the original on 18 June 2022. Retrieved 21 September 2025 – via Foshan Metro Official WeChat Account.
  13. ^ "三号线|水口站~大墩站右线盾构区间顺利贯通" [Line 3 - The right-line shield tunnel section between Shuikou Station and Dadun Station has been successfully completed]. Foshan Railway Investment and Construction Group (in Simplified Chinese). 11 August 2020. Archived from the original on 18 June 2022. Retrieved 21 September 2025 – via Foshan Metro Official WeChat Account.
  14. ^ "3号线|多个土建标段顺利完成单位工程验收" [Line 3 - Multiple civil engineering sections successfully completed unit project acceptance]. Foshan Railway Investment and Construction Group (in Simplified Chinese). Archived from the original on 13 May 2022. Retrieved 21 September 2025 – via Foshan Metro Official WeChat Account.
  15. ^ 尹辅华 (2 November 2021). "佛山地铁三号线新进展:首个土建单位完成验收" [New progress of Foshan Metro Line 3: The first civil engineering unit completes acceptance]. Nanfang Daily (in Simplified Chinese). Archived from the original on 5 November 2021.
  16. ^ "3号线首批5个车站顺利完成临时"三权"移交" [The first batch of 5 stations on Line 3 successfully completed the temporary "three rights" transfer]. Foshan State-owned Assets Supervision and Administration Commission (in Simplified Chinese). 8 June 2022. Archived from the original on 16 July 2022. Retrieved 21 September 2025.
  17. ^ 陈飞龙 (24 December 2022). "官宣!佛山地铁3号线首通段12月28日正式开通" [Official Announcement! The first section of Foshan Metro Line 3 officially opened on December 28th] (in Simplified Chinese). Southern Metropolis Daily. Archived from the original on 24 December 2022. Retrieved 21 September 2025.
  18. ^ 邱日华 (22 May 2025). "提前收车、间隔拉长……佛山地铁"降本"运营,谁受影响?" [Closing trains early, extending intervals... Who is affected by Foshan Metro's "cost-reduction" operations?]. Nanfang Daily (in Simplified Chinese). Archived from the original on 22 May 2025. Retrieved 19 September 2025.