Mahi Banswara Atomic Power Plant
| Mahi Banswara Rajasthan Atomic Power Plant (MBRAPP) | |
|---|---|
| Country | India |
| Location | Banswara, Rajasthan |
| Coordinates | 23°31′46″N 74°35′26″E / 23.52944°N 74.59056°E[1] |
| Construction began | Late 2025 (planned) |
| Construction cost | ₹50,000 crore (US$5.9 billion) |
| Owners | ASHVINI JV - Anushakti Vidhyut Nigam (NPCIL - 51% and NTPC - 49%) |
| Operator | ASHVINI |
| Nuclear power station | |
| Reactor type | IPHWR-700 |
| Reactor supplier | NPCIL/BARC |
| Cooling source | Mahi Bajaj Sagar Dam, Mahi River |
| Power generation | |
| Units planned | 4 x 700 MW |
| Nameplate capacity | 2800 MW |
The Mahi Banswara Rajasthan Atomic Power Plant (MBRAPP) is a planned nuclear power plant to be built on a 1,366.49 acres (553.00 ha) area, near Banswara district of Rajasthan.[2][1]
The project will have an installed capacity of 2800 Megawatts (MW). On 9 May 2025, the Atomic Energy Regulatory Board gave permission for the project.
Prime minister Narendra Modi laid the foundation stone for the plant on September the 25th, 2025 during his visit to Rajasthan. The first unit will commence construction soon thereafter and is expected to be operational in six and a half years according to sources.
History
Nestled in the tribal areas of Rajasthan, the Mahi Banswara project aims to kick start the region by providing jobs and investment opportunity and alleviating the power shortage in the state. The plant construction was scheduled for 2024 and will be jointly developed by NTPC and NPCIL. Along with Chutka Nuclear Power Plant, NTPC aims to generate 3500 MW of electricity from nuclear sources.[3][4]
On 9 May 2025 the Atomic Energy Regulatory Board of India published siting consent for the proposed plant.[5]
On 25th September 2025, Prime Minister Narendra Modi laid the foundation stone at the site, during his visit to Banswara district of Rajasthan. All the clearances have been granted, and the construction is expected to begin in late 2025.
Design and specification
The proposed 700 MW IPHWR-700 reactors are indigenous and similar to the ones in operation at Kakrapar Atomic Power Station (KAPP-3 &4) and Rajasthan unit 8 and the unit currently under construction in Rajasthan Atomic Power Station (RAPP-8).
Cost and economics
The plant is jointly built by the Nuclear Power Corporation of India and National Thermal Power Corporation Limited, the project is estimated to cost ₹50,000 crore (US$5.9 billion). The project is a part of the fleet mode reactor program of the Government of India under which 10 indigenous IPHWR-700 reactors are being built and the goal of 100 GWe nuclear capacity till 2047. The construction is to be started in 2025 and planned to be competed within 4-5 year.[6][7]
Units
| Phase | Unit No. |
Reactor | Status | Capacity in MWe | Construction start | First criticality | Grid Connection | Commercial operation | Closure | Notes | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Type | Model | Net | Gross | |||||||||
| I | 1 | PHWR | IPHWR-700 | Planned | 630 | 700 | N/a | N/a | N/a | 2031 (Planned) | N/a | |
| 2 | PHWR | IPHWR-700 | Planned | 630 | 700 | N/a | N/a | N/a | N/a | N/a | ||
| 3 | PHWR | IPHWR-700 | Planned | 630 | 700 | N/a | N/a | N/a | N/a | N/a | ||
| 4 | PHWR | IPHWR-700 | Planned | 630 | 700 | N/a | N/a | N/a | N/a | N/a | ||
See also
References
- ^ a b "Mahi Banswara Rajasthan Atomic Power Project" (PDF). 12 February 2016.
- ^ "Proposal for Nuclear Power Plants in States". PIB (Press release). 15 March 2018.
- ^ "बांसवाड़ा परमाणु बिजलीघर में दूर होगा का बिजली संकट, जनवरी 2024 में शुरू होगा पहला रिएक्टर". NDTV (in Hindi). 5 September 2023.
- ^ "NTPC eyes 3.5 GW n-power by 2030, in talks for SMRs". Live Mint. 18 April 2023.
- ^ "Consent for Siting of Mahi Banswara Rajasthan Atomic Power Project (MBRAPP - 1 to 4)" (PDF). Atomic Energy Regulatory Board of India. 9 May 2025. Archived (PDF) from the original on 21 May 2025. Retrieved 21 May 2025.
- ^ "India to get 7,000 MW from nuclear power by 2031 as govt grants bulk approval to reactors". Moneycontrol. 6 April 2024.
- ^ "The Government today informed that it has given bulk approval for the installation of ten nuclear reactors". PIB (Press release). 5 April 2023.