Mông Dương is a ward of Quảng Ninh Province, Vietnam. It is the site of the Mông Dương thermal power plant projects designed to reduce Vietnam's dependence on hydropower.
Mông Dương power project
State-owned Electricity of Việt Nam (EVN) plans 2,200 MW of coal-fired power stations at Mông Dương.
- Mông Dương I Thermal Power Plant (1,000 MW) was ADB part financed. The financing framework was signed in 2007.[2] The plant required a total investment of US$1.1 billion. NTP 15-Dec-2011, #1 COD 15-Apr-2015, #2 COD 15-Oct-2015.
Final Completion Ceremony at Site was on 16-Jan-2016. - Boiler Type : CFB (Foster Wheeler China) - Capacity : 250MW * 4 units
- Mông Dương II will sell electricity to Vietnam Electricity (EVN) under a 25-year power purchase agreement (PPA) denominated in US dollars and allowing for a fuel cost pass-through, protecting foreign investors from fluctuations in coal prices. NTP was on 7-Aug-2011, #1 COD was on (Plan/Actual) 04-Dec-2014/09-Mar-2015, #2 COD was on (Plan/Actual) 02-Jun-2015/24-Apr-2015. Final Completion Ceremony was on Hanoi Marriot Hotel, 26-Oct-2015.
- Boiler Type : Downshot - Capacity : 560MW * 2 units
See also
References
- ^ 63/1981/QĐ-HĐBT
- ^ VNGOP – The State Bank of Việt Nam and the Asia Development Bank (ADB) signed a framework financing agreement for the thermal power project Mông Dương 1 on October 09 in Hà Nội. (10/10/2007-07:05:00 AM) "Under the framework agreement, the loan worth of US $931 million from ADB to Mông Dương 1 will be granted in two phases. The first loan of US $28 million was signed on the day. ADB plans to sign the second loan of US $903 million within the next two years."