Gadarwara Super Thermal Power Station
| Gadarwara Super Thermal Power Station | |
|---|---|
NTPC Gadarwara Thermal Power Plant | |
Location of the Gadarwara Super Thermal Power Station in Madhya Pradesh, India | |
| Official name | Gadarwara Super Thermal Power Station |
| Country | India |
| Location | Gadarwara, Narsinghpur district, Madhya Pradesh |
| Coordinates | 22°51′22″N 78°51′24″E / 22.85611°N 78.85667°E |
| Status | Operational (Stage-I); Stage-II Approved |
| Construction began | 2014 |
| Commission date | 2019–2021 |
| Operator | NTPC Limited |
| Thermal power station | |
| Primary fuel | Coal |
| Turbine technology | Supercritical |
| Power generation | |
| Units operational | 2 × 800 MW |
| Units planned | 2 × 800 MW (Stage-II) |
| Nameplate capacity | 1,600 MW (operational) |
| External links | |
| Website | www |
Gadarwara Super Thermal Power Station is a coal-based thermal power station located near Gangai village in Gadarwara tehsil of Narsinghpur district in the Indian state of Madhya Pradesh.[1] The power station is owned and operated by NTPC Limited, India's largest power generation utility.[2] With a planned ultimate capacity of 3,200 MW (4×800 MW), it is one of the major supercritical thermal power projects in central India.[3]
As of 2024, Stage-I of the project, comprising two units of 800 MW each (total 1,600 MW), is fully operational and in commercial operation.[4] Stage-II, consisting of an additional two units of 800 MW each, received investment approval from the NTPC Board in November 2024.[5]
History
Planning and approval
The Gadarwara Super Thermal Power Project was conceived as part of NTPC's expansion plan during India's 12th Five-Year Plan period to add over 14,000 MW of capacity.[6] The project received environmental clearance from the Ministry of Environment, Forest and Climate Change (MoEFCC) on 22 March 2013.[7]
The foundation stone for the project was laid in February 2014 with an initial cost estimate of approximately ₹25,000 crore (US$3.4 billion).[8] NTPC awarded the EPC contract to Bharat Heavy Electricals Limited (BHEL) for the execution of Stage-I of the project.[9]
Construction and commissioning
The first unit (800 MW) achieved grid synchronization on 30 August 2018 at 05:12 AM IST, marking a significant milestone in the project's development.[9] The unit was declared in commercial operation on 30 April 2019, with the revised cost estimate for Stage-I finalized at ₹15,105.22 crore.[1]
The second unit (800 MW) was included in the installed capacity on 18 February 2021 and declared in commercial operation on 1 March 2021.[4] With the commissioning of both units, NTPC's commercial capacity reached 52,115 MW, and the NTPC Group's total capacity reached 64,880 MW as of March 2021.[4]
Stage-II development
The Stage-II expansion (2×800 MW) received investment approval of ₹20,445.69 crore from the NTPC Board on 5 November 2024.[5] The expansion was initially proposed to the Expert Appraisal Committee (EAC) in March 2024 but required additional environmental information.[10] A revised proposal was submitted in August 2024, and tendering for the project commenced in early 2025.[3]
Design and specifications
Technology
The Gadarwara Super Thermal Power Station employs supercritical technology, which operates at higher pressures and temperatures compared to conventional subcritical plants.[11] This technology results in improved thermal efficiency of approximately 38–40% and reduced greenhouse gas emissions per unit of electricity generated.[12]
Equipment and manufacturing
BHEL's comprehensive scope for Stage-I included the design, engineering, manufacturing, supply, erection, and commissioning of major equipment including:[9]
- Supercritical boilers
- Steam turbines rated at 800 MW
- Generators
- Electrostatic precipitators (ESPs)
- Controls and instrumentation systems
- Associated auxiliaries
The equipment was manufactured at various BHEL facilities across India, including Trichy (boilers), Haridwar (turbines), Bhopal (auxiliaries), Ranipet (transformers), Hyderabad (control systems), and Jhansi (boiler auxiliaries).[11]
Performance
The plant is designed to operate at a Plant Load Factor (PLF) of 90%, ensuring high availability and efficient power generation.[1] Both operational units utilize advanced emission control systems to meet India's stringent environmental norms.[13]
Capacity
The project is being developed in two stages:
| Stage | Unit Number | Capacity (MW) | Date of Commercial Operation | Status |
|---|---|---|---|---|
| Stage-I | 1 | 800 | 30 April 2019[1] | Operational |
| 2 | 800 | 1 March 2021[4] | Operational | |
| Stage-II | 3 | 800 | TBD | Approved (under development)[5] |
| 4 | 800 | TBD | Approved (under development)[5] | |
| Total Capacity | 3,200 | |||
Fuel and water supply
Coal supply
The primary fuel source for the power station is coal from the Talaipalli coal block located in Chhattisgarh.[7] The plant requires approximately 8 million tonnes per annum (MTPA) of coal at 90% PLF for its ultimate capacity.[10] The Talaipalli coal block has received environment and forest clearances for coal mining operations.[14]
Water supply
Water for the power station is sourced from the Narmada River, located approximately 30 kilometers from the project site.[6] A dedicated pipeline has been laid from the river to the plant site.[1] The Madhya Pradesh Water Resources Department constructed a small weir on the river to ensure adequate water supply without causing submergence of agricultural lands.[7]
Land acquisition
Land details
According to the Environmental Clearance dated 22 March 2013, the total land requirement for the project is 1,990 acres (approximately 805 hectares).[7] As of 2024, a total of 2,250.40 acres (910.706 hectares) has been acquired for the project.[10]
The land acquisition comprised:[15]
- Barren government land: 318 acres (transferred by Government of Madhya Pradesh)
- Government agricultural land: 45 acres
- Private agricultural land: 1,580 acres (acquired from local farmers)
- Other government land: 47 acres
Affected villages
The land acquisition affected six villages in the Gadarwara region:[6]
- Chor Barhata
- Dongargaon
- Gangai
- Kudari
- Mehra Kheda
- Umaria
Approximately 500 farmers from these villages were affected by the land acquisition process.[15]
Environmental and social issues
Farmer protests
The project has faced significant opposition from local farmers since land acquisition began in 2013.[6] Major protests erupted in December 2017, with farmers alleging broken promises regarding employment opportunities made during the land acquisition phase.[6]
On 12 January 2018, farmers held protests and submitted a memorandum demanding jobs for displaced families.[6] Protests continued for over 15 days, with a massive agitation planned for New Delhi on 23 February 2018.[16] Intermittent protests have continued through subsequent years regarding rehabilitation and employment issues.[17]
Environmental concerns
Local communities have reported several environmental impacts:[15][6]
- Fly ash from the plant affecting nearby agricultural lands
- Reduction in crop production due to ash pollution
- Groundwater pollution in surrounding areas
- Declining groundwater levels
- Respiratory health issues among the local population due to coal dust
NTPC has placed warnings on hand pumps in affected villages indicating that water is not potable, forcing villagers to use contaminated water sources.[15]
Corporate social responsibility
NTPC committed to a one-time investment of ₹45.60 crore for CSR activities during the construction phase and an annual commitment of ₹9.2 crore for development work in affected villages.[7] However, local advocacy groups and civil society organizations have raised concerns about inadequate implementation of these commitments.[17]
Current operations and future expansion
As of 2024, both units of Stage-I (1,600 MW) are fully operational and contribute to the national power grid.[4] The power generated from the station helps meet the energy demands of central India and supports the country's industrial and economic growth.[13]
Stage-II development is progressing with investment approval secured and tendering processes underway.[5] Upon completion of Stage-II, the Gadarwara Super Thermal Power Station will achieve its ultimate capacity of 3,200 MW, making it one of the largest thermal power generation facilities in Madhya Pradesh.[3]
The project is part of NTPC's broader plan to add approximately 13.6 GW of thermal capacity by fiscal year 2026-27, supporting India's target of adding 80 GW of thermal power capacity by 2031-32.[18]
See also
- NTPC Limited
- List of power stations in India
- Supercritical steam generator
- Bharat Heavy Electricals Limited
- List of coal power stations
- Energy in India
References
- ^ a b c d e NTPC 2019.
- ^ Business Standard 2018.
- ^ a b c Economic Times 2024.
- ^ a b c d e NTPC 2021.
- ^ a b c d e Business Standard 2024.
- ^ a b c d e f g Down to Earth 2018.
- ^ a b c d e MoEFCC 2013.
- ^ Times of India 2014.
- ^ a b c BHEL 2018.
- ^ a b c Global Energy Monitor 2024.
- ^ a b BHEL 2019.
- ^ Power Technology 2019.
- ^ a b Central Electricity Authority 2021.
- ^ Ministry of Coal 2018.
- ^ a b c d CFA 2018.
- ^ Hindustan Times 2018.
- ^ a b CFA 2022.
- ^ Ministry of Power 2024.
Citations
- Business Standard (30 August 2018). "BHEL synchronizes first 800 MW unit at NTPC Gadarwara". Business Standard. Retrieved 10 November 2024.
{{cite news}}:|last=has generic name (help)CS1 maint: ref duplicates default (link) - Business Standard (5 November 2024). "NTPC board approves Rs 79,738 crore investment for three thermal projects". Business Standard. Retrieved 10 November 2024.
{{cite news}}:|last=has generic name (help)CS1 maint: ref duplicates default (link) - BHEL (30 August 2018). "BHEL synchronises 800 MW unit at NTPC Gadarwara". Bharat Heavy Electricals Limited. Retrieved 10 November 2024.
{{cite web}}: CS1 maint: ref duplicates default (link) - BHEL (2019). "Supercritical Technology Portfolio". Bharat Heavy Electricals Limited. Retrieved 10 November 2024.
{{cite web}}: CS1 maint: ref duplicates default (link) - Central Electricity Authority (2021). "All India Installed Capacity". Ministry of Power, Government of India. Retrieved 10 November 2024.
{{cite web}}: CS1 maint: ref duplicates default (link) - CFA (2018). NTPC Gadarwara: Environmental and Social Assessment (Report). Centre for Financial Accountability. Retrieved 10 November 2024.
{{cite report}}: CS1 maint: ref duplicates default (link) - CFA (2022). Tracking NTPC's Social and Environmental Commitments (Report). Centre for Financial Accountability. Retrieved 10 November 2024.
{{cite report}}: CS1 maint: ref duplicates default (link) - Down to Earth (1 February 2018). "Gadarwara farmers protest outside collector's office". Down to Earth. Retrieved 10 November 2024.
{{cite news}}: CS1 maint: ref duplicates default (link) - Economic Times (2024). "NTPC begins tendering for Gadarwara Stage-II expansion". The Economic Times. Retrieved 10 November 2024.
{{cite news}}: CS1 maint: ref duplicates default (link) - Global Energy Monitor (2024). "Gadarwara Super Thermal Power Project". Global Energy Monitor. Retrieved 10 November 2024.
{{cite web}}: CS1 maint: ref duplicates default (link) - Hindustan Times (23 February 2018). "Farmers plan massive protest in Delhi over Gadarwara project". Hindustan Times. Retrieved 10 November 2024.
{{cite news}}: CS1 maint: ref duplicates default (link) - Ministry of Coal (2018). "Talaipalli Coal Block Clearances". Ministry of Coal, Government of India. Retrieved 10 November 2024.
{{cite web}}: CS1 maint: ref duplicates default (link) - Ministry of Power (2024). "Power Generation Capacity Addition Targets". Ministry of Power, Government of India. Retrieved 10 November 2024.
{{cite web}}: CS1 maint: ref duplicates default (link) - MoEFCC (22 March 2013). Environmental Clearance for Gadarwara Super Thermal Power Project (Report). Ministry of Environment, Forest and Climate Change, Government of India. Retrieved 10 November 2024.
{{cite report}}: CS1 maint: ref duplicates default (link) - NTPC (30 April 2019). "NTPC declares Unit-1 of Gadarwara in commercial operation" (Press release). NTPC Limited. Retrieved 10 November 2024.
{{cite press release}}: CS1 maint: ref duplicates default (link) - NTPC (1 March 2021). "NTPC declares Unit-2 of Gadarwara STPP in commercial operation" (Press release). NTPC Limited. Retrieved 10 November 2024.
{{cite press release}}: CS1 maint: ref duplicates default (link) - Power Technology (2019). "Supercritical Power Plant Technology Overview". Verdict Media Limited. Retrieved 10 November 2024.
{{cite web}}: CS1 maint: ref duplicates default (link) - Times of India (20 February 2014). "Scindia lays foundation stone of NTPC super thermal power project at Gadarwara". The Times of India. Retrieved 10 November 2024.
{{cite news}}: CS1 maint: ref duplicates default (link)