Blue Line (Namma Metro)

Blue Line
Overview
Other names
  • ORR East Line
  • Airport Metro
  • Line 5
  • Central Silk Board - KIAL Terminals Line
Native nameನೀಲಿ ಮಾರ್ಗ (Nīli mārga)
OwnerBangalore Metro Rail Corporation Limited (BMRCL)
LocaleBangalore, Karnataka, India
Termini
Connecting linesOperational (2):
Purple Line Yellow Line
Upcoming (3):
Red Line Pink Line Orange Line
Stations13 (Phase-2A) + 16 (Phase-2B) = 29
03 (Phase-2B) - Future stations
Websitebmrc.co.in
Service
TypeMetro
SystemNamma Metro
Depot(s)Baiyappanahalli, Doddajala
History
Planned openingPhase 2A - June 2026 (2026-06)
Phase 2B - December 2027 (2027-12)
Technical
Line length58.19 km (36.16 mi)
Number of tracks2
CharacterElevated, At Grade
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC third rail
Blue Line Map (TBC)

Central Silk Board
HSR Layout
Agara
Red Line towards Sarjapura
Ibbaluru
Bellandur
Embassy TechVillage Kadubeesanahalli
Kodibeesanahalli
Marathahalli
ISRO
Indian Railways Towards Hosur and
Banaswadi or Baiyyappanahalli
Doddanekundi
Bagmane Developers - DRDO Sports Complex
Sarasvathi Nagara
Krishnarajapura
Indian Railways Towards Krishnarajapuram and
Yelahanka Jn or Bengaluru Cantt.
Baiyappanahalli Depot (U/C)
Kasturi Nagar
Horamavu
HRBR Layout
Kalyan Nagar
HBR Layout
Nagawara
Pink Line
Under construction
Veerannapalya
Kempapura
Red Line towards Sarjapura
Hebbala
Red Line
Planned
Kodigehalli
Jakkur Cross
Jakkur Plantation (no scope)
Indian Railways Towards
KSR Bengaluru and Yelahanka Jn
Yelahanka
Bagalur Cross
Bettahalasuru (no scope)
Chikkajala (future)
Doddajala
Indian Railways Towards
Kolar and Yelahanka Jn
Doddajala Depot (U/C)
(at-grade)
Airport City
KIAL Terminals

The Blue Line is part of the Namma Metro rail network for the city of Bangalore, Karnataka, India. It consists of two sections - Phase-2A (Central Silk Board to Krishnarajapura) and Phase-2B (Krishnarajapura to Airport). Construction of Phase-2A began in August 2021. Construction of Phase-2B began in February 2022. The 58.19 km line connects Central Silk Board with the Kempegowda International Airport. The Line is mostly elevated but also has 2 at-grade (surface) sections, at the AFS Yelahanka Campus Bengaluru, and the Airport City station, and also has 1 underground section - at the KIA Terminals . There are 31 stations on the line of which 28 are elevated, 2 is at grade, and 1 is underground - making it the second line, after Purple Line, in the Namma Metro system to contain all 3 station types. The Blue Line will have interchanges with the Yellow Line at Central Silk Board, Purple Line at Krishnarajapura, Pink Line at Nagawara and a planned interchange with the proposed Orange Line at Hebbal.

In June 2022, the BMRCL launched the first ever U Girder span on ORR-Airport metro line.[1][2][3] The extension of the Purple Line and construction of the Yellow Line is completed and operational, where Construction of Pink Line is currently under progress. The Pink, Yellow and Blue lines will be CBTC-signaling enabled, unlike Namma Metro's first two lines (Purple and Green lines use distance-signaling). In June 2023, the Deputy Chief Minister of Karnataka D. K. Shivakumar informed that Metro line to Kempegowda International Airport will be completed by December 2026, plus or minus 3 months.[4][5][6][7]

History

History
Phase Section Planned Opening Terminals Length Stations
2A P2A ORR December 2026 Central Silk Board Krishnarajapura 19.75 km (12.27 mi) 13
2B P2B APL December 2027[8] Krishnarajapura Hebbal 11.35 km (7.05 mi) 8
Hebbal KIAL Terminals 27.09 km (16.83 mi) 9
Total Central Silk Board KIAL Terminals 58.19 km (36.16 mi) 30

The routes under Phase-2A and Phase-2B (Blue Line) were at first considered a part of the Phase-3 of metro development, but were prioritized under Phase-2, as the Central Government requested BMRCL to begin work on the airport link as early as February 2012.[9][10]

The route from Central Silkboard to K R Pura along the eastern part of Outer Ring Road (ORR) was included as Phase-2A since development on that part of ORR had leap-frogged much ahead of the rest of the city with huge number of new office buildings. As a result, traffic increased several fold with employees traveling from different parts of the city to this new CBD. Chief Minister of Karnataka, Siddaramaiah announced in September 2016 that a new 18 km (11.2 mi) line connecting Central Silk Board with KR Pura along ORR would be included in Phase 2 as Phase-2A of the project at an estimated cost of ₹4202 crores.[11][12]

Kempegowda International Airport (opened during May 2008) being very far from city center (about 35 km), commuting time by road in traffic congestion is time-consuming. Hence, attention for building a fast mass transit was in the minds of planners from the very beginning, especially since air traffic had kept increasing. The old airport in Bengaluru, the HAL Airport, located well within the city, had closed for commercial operations as part of the terms of the PPP for the new airport.

To connect airport to city, there had initially been a proposal to build a 33 km (21 mi) high speed rail line from MG Road to Kempegowda International Airport (KIA). Cost was estimated at ₹5,767 crore (US$810 million). This was to be executed by an independent SPV - Bangalore Airport Rail Link Limited (BARLL).[13] However, the plan for an exclusive city-airport high speed rail was canceled during October 2013 due to high cost and viability concerns.[14]

It was decided that BMRCL would manage the airport rail project and a regular metro line with fewer halts would be built instead of a high speed rail. Following this, suggestions were invited from public during September 2016 to choose any one of nine possible extension routes from existing and proposed metro lines to the airport.[15] The proposed extension routes had an average length of 30 km (19 mi), and cost estimates ranged between ₹4,500 crore and ₹7,000 crore. A 25.9 km (16.1 mi) extension from Nagawara via Kannur and Bagaluru was the shortest, while the 35.4 km (22.0 mi) extension from Yeshwanthpur via Yelahanka, Kannur and Bagaluru was the longest of the proposed routes. BMRC received 1,300 responses from the public.[16] The shortest (25.9 km, 16.1 mi) extension of the Kalena Agrahara (previously Gottigere) – Nagawara line via Kannur and Bagaluru to the airport emerged as the most popular choice.[17] In February 2017, the Centre requested BMRC to start work on the airport link before Phase 3. Thus, the Airport Line was included in Phase 2 as Phase 2B.[18]

Since the airport's managing company, Bengaluru International Airport Limited (BIAL) forbade underground construction from the southern side of the airport due to security concerns as it would have to pass beneath the airport's second runway, the shortest route options (i.e. extending the Pink line from Nagawara directly north) were eliminated. An alternate route proceeding north till RK Hegde Nagar and then turning west to Jakkur and then along Airport Road was explored. Bangalore Development Minister K. J. George announced on 12 May 2017 that the government had finalized the Nagawara—Ramakrishna Hegde Nagar—Jakkur—Yelahanka route to the airport.[19] However, this route had an obstacle as a high-pressure petroleum pipeline was passing through the originally proposed route.[20]

This was changed and on 10 January 2019, the State Cabinet approved a change in alignment for the proposed metro line to the airport. The new line would begin at Krishnarajapura (K.R. Pura) and be aligned along the northern part of ORR (Outer Ring road), passing Kasturinagar, Nagawara, Hebbal, and Jakkur before heading towards the airport. The line would be 38 km (23.6 mi) long, about 9 km (5.6 mi) longer than the route previously proposed, estimated to cost ₹10,584 crore (US$1.5 billion).[21]

Tendering

Blue Line
Pre-Construction Activity
Tendering Section Activity Successful Bid /Cost Contractor Award
Phase-2A/ORR/2018/Demolition/DLN-9/35 Central Silk Board to K. R. Pura Demolition 2.24 crore (US$260,000) B R Chawla Demolition 12 Oct 2018
Phase-2A & 2B/Via & Stns /PMC/2020/72 Central Silk Board to KIAL Project Management Consultant 20.58 crore (US$2.4 million) RITES 17 Dec 2021
Phase-2A&2B/DDC/Sec-1 Central Silk Board - HBR Layout Detailed Design Consultant 8.30 crore (US$980,000) SMEC International 07 Feb 2020
Phase-2A&2B/DDC/Sec-2 HBR Layout - KIAL Airport Detailed Design Consultant 6.26 crore (US$740,000) AECOM – CEG JV 12 Feb 2020
Airport Depot & Byp Depot/DDC/2021/76 Baiyappanahalli & Airport Depot Detailed Design Consultant 3.94 crore (US$470,000) AECOM – CEG JV 16 Sept 2021
CE-US/ELE/EHV/ORR/PH-2A Central Silk Board to K.R. Pura Conversion of Electrical Lines 19.13 crore (US$2.3 million) Rahul Cables 13 May 2022
Miscellaneous KR Pura - KIAL Airport 9.27 crore (US$1.1 million) Various 19 Dec 2020
Total 69.72 crore (US$8.2 million)
Civil Work
Tendering Section Length Successful Bid /Cost Contractor Award
Package 2A/P1/60(a) Central Silk Board - Kodibeesanahalli 9.859 km (6.126 mi) 785.25 crore (US$93 million) Afcons 25 May 2021
Package 2A/P2/60(b) Kodibeesanahalli - KR Pura 9.774 km (6.073 mi) 623.55 crore (US$74 million) Shankaranarayana 25 May 2021
Package 2B/P2/69(a) KR Pura - Kempapura 11.003 km (6.837 mi) 739.04 crore (US$87 million) NCC 17 Nov 2021
Package 2B/P2/69(b) Kempapura - Bagalur Cross 11.678 km (7.256 mi) 747.99 crore (US$88 million) NCC 17 Nov 2021
Package 2B/P2/69(c) Bagalur Cross - KIAL Terminals 15.011 km (9.327 mi) 680.21 crore (US$80 million) NCC 17 Nov 2021
Veerannapalya Station[22] 35.74 crore (US$4.2 million) URC Constructions 07 Feb 2025
Total 58.19 km (36.16 mi) 3,611.78 crore (US$430 million)
Depot Work
Tendering Successful Bid /Cost Contractor Award
Remodelling Baiyappanahalli Depot 249.19 crore (US$29 million) J Kumar – AICPL JV 18 Mar 2023
Airport Depot 182.39 crore (US$22 million) J Kumar – AICPL JV 18 Mar 2023
Total 431.58 crore (US$51 million)
Architectural Finishing Works
Tendering Successful Bid /Cost Contractor Award
Package 2A-A1 Central Silk Board - Kadubeesanahalli 65.58 crore (US$7.8 million) MR Constructions 16 Dec 2024
Package 2A-A2 Kodibeesanahalli - KR Pura 66.78 crore (US$7.9 million) Godrej & Boyce 09 Nov 2024
Phase-2B/Arch. Works/A2/RT/2025/136 Hebbal - Doddajala Bidding Underway
Phase-2B/Arch. Works/A1/2025/129 Kasturi Nagar - Kempapura Tenders under evaluation
Total 132.36 crore (US$16 million)
Miscellaneous
Tendering Successful Bid /Cost Contractor Award
Land Acquisition 2,762 crore (US$330 million) N/A 2020
Phase-2A and 2B/Plantations/2023/95 Plantation and Maintenance of Trees 7.29 crore (US$860,000) Various 28 Mar 2023
Phase-2A and 2B/Track Work/2022/93 Ballastless Track Work 500.94 crore (US$59 million) Larsen & Toubro 02 Jun 2023
5RS-DM Rolling Stock (222 Coaches) 2,217.78 crore (US$260 million) BEML 08 Aug 2023
Phase-2A & 2B/Turnouts /2023/101 Track Turnout 29.98 crore (US$3.5 million) Vossloh 22 Mar 2024
EPC6-CC Engineering, Supply, Erection, Testing and Commissioning of Power Supply 248.61 crore (US$29 million) KEC International 10 Jun 2024
EPC5-CC 750V DC Third Rail electrification 764.64 crore (US$90 million) SiemensRVNL JV 11 Jun 2024
Signalling System (CBTC) & PSD 548.48 crore (US$65 million) Alstom 12 Jun 2024
Phase II/ 9 ESCAL - DM Elevators & Escalators 203.08 crore (US$24 million) Johnson Lifts 6 Feb 2025
E&M-6 Electrical & Mechanical 197.04 crore (US$23 million) Jakson 7 Feb 2025
Phase II/6 ELEV-DM Machine Room Less Gearless Elevators 45.31 crore (US$5.4 million) 20 Mar 2025
Phase-2B/Arch. Works/A1/2025/129 Automatic Fare Collection System Tenders Under Evaluation
Total 7,435.15 crore (US$880 million)
Total Line Cost 11,680.59 crore (US$1.4 billion)

Phase-2A

BMRCL prepared the detailed project report for the proposed Central Silk Board - KR Pura Line and submitted the DPR to the state government on 28 October 2016. Phase 2A was approved by the State Cabinet on 1 March 2017.

Tenders for the ORR (East) Metro line were called in February 2018 and IL&FS emerged the lowest bidder for all packages. However, the tenders were quashed due to cash flow problems and bankruptcy proceedings by the selected firm, IL&FS. A second round of tendering was done in December 2019.[23] The project cost was revised to ₹5994 crores.[23] Fresh bids were received by multiple firms in March 2020.[24][25] There are two packages. The first package included 2.84 km of ramps for a flyover at Central Silk board junction in addition to 9.859 km of viaduct with six elevated stations. The second package was for 8.377 km viaduct with seven elevated stations, 1.097 km depot line and a 0.30 km pocket track.

Central government's approval was much delayed[26][27] and finally received in April-2021.[28] Tenders were awarded in May-2021 and construction on Phase-2A finally began in August-2021.[29] Opening of this phase as per August 2022 from MD of BMRCL is expected around December 2026.

Phase-2B

Installation of U-Girders (Hebbala - KIAL Terminals stretch) under Blue Line of Namma Metro as of October 2024

DPR for the Airport Line had been prepared in September 2017[30][31] and cleared by Government of Karnataka in January 2019.[21]

Tenders for the Airport line were called in July 2020. There are three packages. The first package was for 11.003 km viaduct, including 281 mtrs viaduct beyond Phase-2A with eight elevated stations and 650 mtrs link line to Baiyyappanahalli depot. The second package was for 11.678 km viaduct with 250 mtrs pocket track and two elevated stations. The third package was for 15.011 km viaduct, including 718.18 mtrs cut and cover portion in front of Yelahanka Air Force Station. All three packages include road widening, utility diversion and allied works.

Bettadahalasuru station would be built by Embassy group at a cost of ₹140 crore. Kempegowda International Airport is likely to fund the construction of two airport stations off the highway.[32][33] An MoU was signed between BMRC and KIAL for construction of the 4.95 km (3.08 mi) line and stations entailing an investment of ₹800 crore.

Central government's approval was delayed[26][27] and finally received in April 2021.[28] Nagarjuna Construction Company (NCC) emerged as the lowest bidder to construct the line on September 16, 2021. Construction finally began in February 2022. Opening of this phase as per August 2022 from MD of BMRCL is expected around December 2025.

Veerannapalya Station was initially awarded to NCC as part of Package 2B/P2/69(a). However, due to a severe delay in shifting an underground gas pipeline the station was unloaded from NCC scope of work. BMRCL re-invited tenders for this station, which was later awarded to URC Constructions.

Controversies and Accidents

In January 2023, an accident occurred wherein a reinforcement cage of an under-construction metro pier fell onto a woman - Tejaswini Sulakhe - and her son Vihan in HBR Layout,[34][35] which led to their death.[36][37] In respose, BMRCL announced a financial assistance package of 20 lakh to the victims' family.[38][39] Separately, Chief Minister Basavaraj Bommai also announced a separate compensation of 10 lakh for each victim, taken from the Chief Ministers’ Relief Fund.[40][41]

Funding

In totality, the 58.19-km line consisting of both Phase 2A and 2B is estimated to cost ₹14,788 crores.[42][43]

The Union and State governments will contribute ₹3,973 crore by way of equity and subordinate debt. Land acquisition costs, estimated at ₹2,762 crore, will be funded by the Government of Karnataka. BMRCL will raise the remaining amount of ₹5,960 crores through loans. In March 2021, it entered into a loan agreement with Japan International Cooperation Agency (JICA) for US$318 million (₹2,317 crore). BMRCL also raised US$500 million (₹3,643 crore) from the Asian Development Bank (ADB) to fund construction of the Blue Line (Phase 2A and 2B).[44][45]

On June 10, 2024, Rail Vikas Nigam Ltd. (RVNL) disclosed in a BSE filing that its joint venture with Siemens had secured a contract worth approximately ₹762 crore from Bangalore Metro Rail Corporation. This contract encompasses the 750V DC third rail electrification work under package EPC5-CC for the 57 km Blue Line of the Namma Metro.[46]

Stations

The Blue Line will have 29 stations.

Interchanges

Passenger interchange facilities, connecting to other metro and railway lines, will be provided at the following stations:

Blue Line
Phase # Station Name Expected Opening [47] Connections Station Layout Platform Level Type
English Kannada
2A 1 Central Silk Board ಕೇಂದ್ರ ರೇಷ್ಮೆ ಮಂಡಳಿ December 2026 Yellow Line Elevated Side
2 HSR Layout ಎಚ್‌ ಎಸ್‌ ಆರ್ ಬಡಾವಣೆ December 2026 Elevated Side
3 Agara ಅಗರ December 2026 Red Line (Approved) Elevated Side
4 Ibbaluru ಇಬ್ಬಲೂರು December 2026 Red Line (Approved) Elevated Side
5 Bellanduru ಬೆಳ್ಳಂದೂರು December 2026 Elevated Side
6 Embassy TechVillage Kadubeesanahalli ಎಂಬೆಸ್ಸಿ ಟೆಕ್ ವಿಲೇಜ್ ಕಾಡುಬೀಸನಹಳ್ಳಿ December 2026 Elevated Side
7 Kodibeesanahalli ಕೋಡಿಬೀಸನಹಳ್ಳಿ December 2026 Elevated Side
8 Marathahalli ಮಾರತಹಳ್ಳಿ December 2026 Elevated Side
9 ISRO ಇಸ್ರೋ December 2026 Elevated Side
10 Doddanekundi ದೊಡ್ಡನೆಕ್ಕುಂದಿ December 2026 Elevated Side
11 Bagmane Developers - DRDO Sports Complex ಬಾಗ್ಮನೆ ಡೆವಲಪರ್ಸ್ - ರ.ಸಂ.ಅ.ಸಂ. ಕ್ರೀಡಾ ಸಂಕೀರ್ಣ December 2026 Elevated Side
12 Saraswathi Nagar ಸರಸ್ವತಿ ನಗರ December 2026 Elevated Side
13 Krishnarajapura (K.R.Pura) ಕೃಷ್ಣರಾಜಪುರ (ಕೆ.ಆರ್.ಪುರ) December 2026 Purple Line
Krishnarajapuram
Elevated Side
2B 14 Kasturi Nagar ಕಸ್ತೂರಿ ನಗರ December 2027 Elevated Side
15 Horamavu ಹೊರಮಾವು December 2027 Elevated Side
16 HRBR Layout ಎಚ್‌ ಆರ್‌ ಬಿ ಆರ್ ಬಡಾವಣೆ December 2027 Elevated Side
17 Kalyan Nagar ಕಲ್ಯಾಣ ನಗರ December 2027 Elevated Side
18 HBR Layout ಎಚ್‌ ಬಿ ಆರ್ ಬಡಾವಣೆ December 2027 Elevated Side
19 Nagawara ನಾಗವಾರ December 2027 Pink Line (Under Construction) Elevated Side & Island
20 Veerannapalya ವೀರಣ್ಣಪಾಳ್ಯ December 2027 Elevated Side
21 Kempapura ಕೆಂಪಾಪುರ December 2027 Orange Line (Approved) Elevated Side
22 Hebbal ಹೆಬ್ಬಾಳ December 2027 Orange Line (Approved);

Red Line (Approved)

Elevated Side
23 Kodigehalli ಕೊಡಿಗೇಹಳ್ಳಿ December 2027 Elevated Island
24 Jakkur Cross ಜಕ್ಕೂರು ಕ್ರಾಸ್ December 2027 Elevated Island
25 Yelahanka ಯಲಹಂಕ December 2027 Elevated Island
26 Bagalur Cross ಬಾಗಲೂರು ಕ್ರಾಸ್ December 2027 Elevated Island
27 Chikkajala* ಚಿಕ್ಕಜಾಲ* December 2027 Elevated TBC
28 Doddajala ದೊಡ್ಡಜಾಲ December 2027 Elevated Island
29 Airport City ವಿಮಾನ ನಿಲ್ದಾಣ ನಗರ December 2027 Airport City (Proposed) At-Grade Side
30 KIAL Terminals ಕೆಂಪೇಗೌಡ ಅಂತಾರಾಷ್ಟ್ರೀಯ ವಿಮಾನ ನಿಲ್ದಾಣ December 2027 Kempegowda International Airport Underground Island

* - Future Station

See also

References

  1. ^ "Bengaluru: Namma Metro's first U-girder launched on ORR". The Times of India. 19 June 2022.
  2. ^ "BMRCL launches U Girder for the first time on ORR-Airport metro line". The Hindu. 19 June 2022.
  3. ^ "BMRCL to switch to U-girders for ORR, KIA Metro lines". The Times of India. 16 September 2019.
  4. ^ "Metro line to Bengaluru Airport to be ready by June 2026: D K Shivakumar".
  5. ^ "Karnataka deputy CM DK Shivakumar clarifies on upcoming new metro lines in Bengaluru. Details".
  6. ^ "Namma Metro link to Bengaluru airport will be completed by June 2026: Governor". The Hindu. 12 February 2024. ISSN 0971-751X. Retrieved 12 February 2024.
  7. ^ "Bengaluru Metro Update: BMRCL MD Urges Fast-Tracking of Airport Line". Deccan Herald. Retrieved 1 August 2025.
  8. ^ Hindu, The. "Bengaluru's Blue Line of Namma Metro scheduled for completion by Dec. 2027".
  9. ^ "DPR for Metro link to BIA in five months". Deccan Herald. 3 November 2012. Retrieved 8 October 2020.
  10. ^ "Bangalore Metro Rail yet to decide on route for Airport Line". Archived from the original on 12 August 2019.
  11. ^ "Metro line from Silk Board to KR Puram to be fast-tracked". The Times of India. 15 September 2016. Retrieved 10 September 2020.
  12. ^ "KR Puram-Silk Board Metro line gets Cabinet approval". Deccan Herald. 2 March 2017. Retrieved 10 September 2020.
  13. ^ "Bangalore High-Speed Rail Link". Railway Technology. Retrieved 10 September 2020.
  14. ^ "Cost, viability nix high-speed rail link to Bengaluru International Airport". The Times of India. 19 October 2013. Retrieved 10 September 2020.
  15. ^ "Now, suggest a Namma Metro route to the airport". Deccan Herald. 15 September 2016. Retrieved 10 September 2020.
  16. ^ "Central funding brightens prospects of metro line to Bengaluru airport". The Hindu. 14 January 2017. ISSN 0971-751X. Retrieved 10 September 2020.
  17. ^ Kidiyoor, Suchith (7 December 2016). "Bengaluru wants KIA Metro line via Nagawara". Bangalore Mirror. Retrieved 10 September 2020.
  18. ^ "Bangalore Metro Rail yet to decide on route for Airport Line – RailNews Media India Ltd". Retrieved 10 September 2020.
  19. ^ "Govt finalises KIA metro link route". Deccan Herald. 13 May 2017. Retrieved 10 September 2020.
  20. ^ "Bengaluru Metro airport line to now run through Hebbal". The New Indian Express. Retrieved 10 September 2020.
  21. ^ a b "Karnataka government clears suburban rail project, Metro to airport". The Times of India. 11 January 2019. Retrieved 10 September 2020.
  22. ^ Veerannapalya Station was initially awarded to NCC as part of Package 2B/P2/69(a). However, due to a severe delay in shifting an underground gas pipeline the station was unloaded from NCC scope of work. BMRCL re-invited tenders for this station, which was later awarded to URC Constructions.
  23. ^ a b "Bengaluru: Dead lines of Namma Metro". Deccan Herald. 25 January 2020. Retrieved 10 September 2020.
  24. ^ "9 Companies Bid for Namma Metro's ORR Project". Urban Railways. 16 March 2020. Retrieved 10 September 2020.
  25. ^ "Namma Metro ORR line tender receives 14 bids". The New Indian Express. Archived from the original on 4 April 2023. Retrieved 10 September 2020.
  26. ^ a b Singh, Neha (4 June 2020). "BMRCL expecting central nod on ORR Metro Corridor in Next 3 months". Metro Rail News. Retrieved 10 September 2020.
  27. ^ a b Menezes, Naveen. "Bengaluru Metro Corp to Blame for ORR, Airport Lines Delay?". The Economic Times. Retrieved 10 September 2020.
  28. ^ a b "Bengaluru Metro: Govt approves 58-km phase 2 project, to cost 14,788 crore". mint. 20 April 2021. Retrieved 21 August 2021.
  29. ^ "Soil testing marks start of work on Namma Metro ORR line". The New Indian Express. Retrieved 21 August 2021.
  30. ^ "Kempe Gowda International Airport Metro link DPR ready, but for Phase 2 or 3?". Bangalore Mirror. 5 October 2017. Retrieved 10 September 2020.
  31. ^ "Bengaluru Metro | BMRC plans two metro stations at Bengaluru Airport". Metro Rail News. 27 September 2017. Retrieved 10 September 2020.
  32. ^ "Public-Private Partnership between Bangalore Metro Rail Corporation Limited (BMRCL) and Bangalore International Airport Limited (BIAL) for Airport section of the ORR-Airport Metro: Signing of MoU". Public-Private Partnership between Bangalore Metro Rail Corporation Limited (BMRCL) and Bangalore International Airport Limited (BIAL) for Airport section of the ORR-Airport Metro: Signing of MoU. Retrieved 10 September 2020.
  33. ^ "Embassy Group signs MoU with BMRCL for Bettahalasur Metro Station". Moneycontrol. 8 September 2020. Retrieved 10 September 2020.
  34. ^ "Metro pillar crash: Sudden loss leaves Bengaluru family shattered". The Times of India. 12 January 2023.
  35. ^ "'I wish I had died too': Husband recalls Bengaluru metro accident horror". 11 January 2023.
  36. ^ "Bengaluru metro structure falls; techie, kid killed". The Times of India. 11 January 2023.
  37. ^ "What caused the under-construction metro pier in Bengaluru to fall?". 11 January 2023.
  38. ^ "Metro structure falls on family of 4, kills mother & toddler-son in Bengaluru". The Times of India. 11 January 2023.
  39. ^ "I regret not insisting on her to work from home, says mother-in-law of Bengaluru Metro pillar collapse victim". 10 January 2023.
  40. ^ "'I will pay you Rs 1 crore. Can you bring back my daughter and grandson?': Bengaluru Metro pillar collapse victim's father". 11 January 2023.
  41. ^ "Bengaluru News Highlights: Woman, her son die after under-construction metro pillar collapses in Hennur CM Bommai announces Rs 10 lakh compensation each". 9 January 2023.
  42. ^ "BMRCL signs loan agreement with ADB". The Hindu. 20 August 2021. ISSN 0971-751X. Retrieved 21 August 2021.
  43. ^ "Project Summary". www.cspm.gov.in. Retrieved 26 May 2025.
  44. ^ "Metro Seeks ₹3.5k cr from ADB - The Economic Times - Bangalore, 2/26/2019". epaper.timesgroup.com. Retrieved 10 September 2020.
  45. ^ "ADB approves $500 million loan for Silk Board-airport metro". Deccan Herald. 9 December 2020. Retrieved 21 August 2021.
  46. ^ Staff Reporter (12 June 2024). "Bangalore Metro: Siemens - RVNL JV Bags Rs. 762 Crore Electrification Contract Of Blue Line - Metro Rail News". Retrieved 12 June 2024.
  47. ^ B.P, Darshan Devaiah (29 November 2024). "Bengaluru metro's Pink Line to be opened by December 2025; Blue Line to KIA by 2026". The Hindu. ISSN 0971-751X. Retrieved 29 November 2024.